SR 7 Extension
Segment from Okeechobee Boulevard to 60th Street (229664-4):
Design Complete – Second Quarter 2021
Construction Complete – Fourth Quarter 2024
Segment from 60th Street to Northlake Boulevard (229664-3):
Design Complete – Second Quarter 2021
Construction Complete – Fourth Quarter 2024
- September 20, 2020: Permit application submitted to SFWMD
- January 28, 2021: Virtual Public Workshop
- February 2021: Anticipated application package submitted to ACOE
- May 2021: Production (plans complete)
- September 2021: Letting
- January 2022: Begin Construction